NAK Crisis Management teams were immediately dispatched to damaged areas after heavy snowfall in Gilan Province, which consequently caused several problems such as power and communication network outages. These teams have successfully stabilized the network and reduced the number of incidents from 375 to 6.

It is notable to consider that crisis management teams not only did a great job in the PM project, but also they repaired power generators to solve the power outage problem for the region, especially for BTS sites. These measures were taken in severe weather conditions to relieve Gilan citizens.

The excellent performance in repairing and stabilizing the network in harsh conditions became possible by the support and efforts from all staff and line teams of NAK. We warmly thank them and wish best for our dear colleagues.